Informational meetings will be held on the first Wednesday of every month at Escanaba City Hall. City Staff, C2AE Engineering Staff, and Contractors will be providing information and be available for questions regarding projects. May’s meeting will focus on:
Water Main Replacements
Location | Possible Timeline |
Bay Street & Veteran Park Area | In Process |
S 18th Street (7th – 9th Ave S) | May 1st |
S 18th Street (1st – 5th Ave S) | Mid-May |
Lead Service Line Replacements
Location | Possible Timeline |
800-900 Blocks Lake Shore Drive | Completed |
1100-1200 Blocks of N 16th Street | Completed |
1300, 1400, and 1500 Blocks of N 16th Street | Current – Completed |
South Lincoln Rd from Ludington to City Limits | Mid-May Pending MDOT Approval Process |
1100-1600 Blocks of N 18th Street | Current in process |
20 sites across town with leaks or problems. See Web Site for detailed list of addresses. |
May 6th |
5th Ave S from Willow Creek Rd to S 26th St. | TBD |
Wastewater
Location | Possible Timeline |
Ludington Lift Station Replacement | TBD |
Sewer Main Replacements on Ludington St | TBD |
For any questions or concerns, please contact Michael Humbert or Jeff Lampi from the City of Escanaba W/WW Departments at 906.786.3291.